From 03/24/2025 to 04/22/2025
04/18/2025
-
updated by
Jules Verrier on 04/18/2025 11:16 AM - The changes were retracted.
04/13/2025
-
updated by
OpenProject Admin on 04/13/2025 01:09 PM - File 1000049346.jpg added as attachment
04/11/2025
-
updated by
Shrinija Poudel on 04/11/2025 03:32 PM - Finish date changed from 03/14/2025 to 03/21/2025
- Start date changed from 03/14/2025 to 03/21/2025
-
updated by
Shrinija Poudel on 04/11/2025 03:32 PM - Dates changed by changes to related Task #110: A.07.3. Demolition of the stairs
- Finish date changed from 03/17/2025 to 03/21/2025
- Duration changed from 46 days to 50 days
-
updated by
Shrinija Poudel on 04/11/2025 03:32 PM - Dates changed by changes to related Task #110: A.07.3. Demolition of the stairs
- Finish date changed from 03/17/2025 to 03/21/2025
- Start date changed from 03/10/2025 to 03/14/2025
-
updated by
Shrinija Poudel on 04/11/2025 03:32 PM - Finish date changed from 03/10/2025 to 03/21/2025
- Start date changed from 03/10/2025 to 03/21/2025
-
updated by
Shrinija Poudel on 04/11/2025 03:31 PM - Finish date set to 03/17/2025
- Start date set to 03/17/2025
- Duration set to 1 day
-
updated by
Shrinija Poudel on 04/11/2025 03:31 PM - Dates changed by changes to related Task #109: A.07.2. Demolition of the walls
- Finish date changed from 03/14/2025 to 03/17/2025
- Duration changed from 45 days to 46 days
-
updated by
Shrinija Poudel on 04/11/2025 03:31 PM - Dates changed by changes to related Task #109: A.07.2. Demolition of the walls
- Finish date changed from 03/14/2025 to 03/17/2025
- Duration changed from 5 days to 6 days
-
updated by
Shrinija Poudel on 04/11/2025 03:31 PM - Finish date set to 03/17/2025
- Start date set to 03/14/2025
- Duration set to 2 days
-
updated by
Shrinija Poudel on 04/11/2025 03:29 PM - Dates changed by changes to related Task #98: A.05.1. Paint internal walls
-
updated by
Shrinija Poudel on 04/11/2025 03:29 PM - Finish date set to 02/24/2025
- Start date set to 02/21/2025
- Duration set to 2 days
-
updated by
Shrinija Poudel on 04/11/2025 03:28 PM - Finish date set to 03/03/2025
- Start date set to 03/03/2025
- Duration set to 1 day
-
updated by
Shrinija Poudel on 04/11/2025 03:28 PM - Finish date set to 02/28/2025
- Start date set to 02/28/2025
- Duration set to 1 day
-
updated by
Shrinija Poudel on 04/11/2025 03:27 PM - Finish date changed from 03/07/2025 to 03/10/2025
- Start date changed from 03/07/2025 to 03/10/2025
-
updated by
Shrinija Poudel on 04/11/2025 03:27 PM - Finish date changed from 02/28/2025 to 02/21/2025
- Start date changed from 02/17/2025 to 02/14/2025
- Duration changed from 10 days to 6 days
-
updated by
Shrinija Poudel on 04/11/2025 03:26 PM - Dates changed by changes to related Task #96: A.03.3. Flooring tiles finish
- Finish date changed from 02/24/2025 to 03/03/2025
- Start date changed from 02/21/2025 to 02/24/2025
- Duration changed from 2 days to 6 days
-
updated by
Shrinija Poudel on 04/11/2025 03:26 PM - Finish date changed from 02/21/2025 to 03/03/2025
- Start date changed from 02/21/2025 to 03/03/2025
-
updated by
Shrinija Poudel on 04/11/2025 03:26 PM - Dates changed by changes to related Task #95: A.03.2. Flooring tiles
- Start date changed from 02/14/2025 to 02/21/2025
- Duration changed from 7 days to 2 days
-
updated by
Shrinija Poudel on 04/11/2025 03:26 PM - Finish date changed from 02/14/2025 to 02/24/2025
- Start date changed from 02/14/2025 to 02/24/2025
-
updated by
Shrinija Poudel on 04/11/2025 03:25 PM - Dates changed by changes to related Task #94: A.03.1. Cement screed
- Finish date changed from 02/21/2025 to 02/24/2025
- Start date changed from 02/10/2025 to 02/14/2025
- Duration changed from 10 days to 7 days
-
updated by
Shrinija Poudel on 04/11/2025 03:25 PM - Finish date changed from 02/10/2025 to 02/24/2025
- Start date changed from 02/10/2025 to 02/24/2025
-
updated by
Shrinija Poudel on 04/11/2025 03:25 PM - Dates changed by changes to related Task #87: A.02.2. Staircase step/grades
- Finish date changed from 02/07/2025 to 02/10/2025
- Start date changed from 01/24/2025 to 02/07/2025
- Duration changed from 11 days to 2 days
-
updated by
Shrinija Poudel on 04/11/2025 03:25 PM - Finish date changed from 01/27/2025 to 02/10/2025
- Start date changed from 01/24/2025 to 02/10/2025
- Duration changed from 2 days to 1 day
-
updated by
Shrinija Poudel on 04/11/2025 03:25 PM - Dates changed by changes to related Task #86: A.02.1. Staircase walls
- Finish date changed from 01/27/2025 to 02/07/2025
- Start date changed from 01/20/2025 to 01/24/2025
- Duration changed from 6 days to 11 days
-
updated by
Shrinija Poudel on 04/11/2025 03:25 PM - Finish date changed from 01/20/2025 to 02/07/2025
- Start date changed from 01/20/2025 to 02/07/2025
-
updated by
Shrinija Poudel on 04/11/2025 03:24 PM - Dates changed by changes to related Task #84: A.01.2. Brick walls Type 2
- Finish date changed from 02/07/2025 to 02/03/2025
- Duration changed from 16 days to 12 days
-
updated by
Shrinija Poudel on 04/11/2025 03:24 PM - Finish date changed from 02/07/2025 to 02/03/2025
- Duration changed from 10 days to 6 days
-
updated by
Shrinija Poudel on 04/11/2025 03:24 PM - Finish date changed from 01/17/2025 to 01/24/2025
- Duration changed from 1 day to 6 days
-
updated by
Jules Verrier on 04/11/2025 01:20 PM - Scheduling mode set to Automatic
-
updated by
Jules Verrier on 04/11/2025 01:20 PM - Scheduling mode set to Automatic
-
updated by
Jules Verrier on 04/11/2025 01:19 PM - Subject changed from A.06. Paint walls to A.05. Paint walls
-
updated by
Jules Verrier on 04/11/2025 01:19 PM - Subject changed from A.06.1. Paint internal walls to A.05.1. Paint internal walls
-
updated by
Jules Verrier on 04/11/2025 10:29 AM - Dates changed by changes to related Phase #108: A.07. Dismantle
- Finish date changed from 03/07/2025 to 03/14/2025
- Duration changed from 40 days to 45 days
-
updated by
Jules Verrier on 04/11/2025 10:29 AM - Parent set to A.00. Project
-
updated by
Jules Verrier on 04/11/2025 10:29 AM - Parent set to A.00. Project
-
updated by
Jules Verrier on 04/11/2025 10:29 AM - Dates changed by changes to related Phase #90: A.04. Wall finish
- Finish date changed from 02/21/2025 to 03/07/2025
- Duration changed from 30 days to 40 days
-
updated by
Jules Verrier on 04/11/2025 10:29 AM - Parent set to A.00. Project
-
updated by
Jules Verrier on 04/11/2025 10:28 AM - Dates changed by changes to related Phase #93: A.03. Floorings
- Finish date changed from 02/07/2025 to 02/21/2025
- Duration changed from 20 days to 30 days
-
updated by
Jules Verrier on 04/11/2025 10:28 AM - Parent set to A.00. Project
-
updated by
Jules Verrier on 04/11/2025 10:28 AM - Subject changed from A. Project to A.00. Project
-
updated by
Jules Verrier on 04/11/2025 10:28 AM - Parent set to A.00. Project
-
updated by
Jules Verrier on 04/11/2025 10:28 AM - Dates changed by changes to related Phase #82: A.01. Walls
- Finish date changed from 01/13/2025 to 02/07/2025
- Duration changed from 1 day to 20 days
-
updated by
Jules Verrier on 04/11/2025 10:28 AM - Parent set to A.00. Project
-
updated by
Jules Verrier on 04/11/2025 10:28 AM - Dates changed by changes to related closedPhase #78: A.00. Preparation
- Finish date set to 01/13/2025
- Start date set to 01/13/2025
- Duration set to 1 day
-
updated by
Jules Verrier on 04/11/2025 10:28 AM - Parent set to A.00. Project
-
created by
Shrinija Poudel on 04/11/2025 10:25 AM -
updated by
Jules Verrier on 04/11/2025 10:22 AM - Subject changed from A.05.3. Wall tiles to A.04.3. Wall tiles
-
updated by
Jules Verrier on 04/11/2025 10:22 AM - Subject changed from A.05.2 . Plaster external walls to A.04.2 . Plaster external walls
-
updated by
Jules Verrier on 04/11/2025 10:22 AM - Subject changed from A.05.1. Plaster interior walls to A.04.1. Plaster interior walls
-
updated by
Jules Verrier on 04/11/2025 10:22 AM - Subject changed from A.05. Wall finish to A.04. Wall finish
-
created by
Jules Verrier on 04/11/2025 10:20 AM -
updated by
Jules Verrier on 04/11/2025 10:09 AM - Subject changed from A.06.3. Wall tiles to A.05.3. Wall tiles
- Parent set to A.04. Wall finish
-
updated by
Jules Verrier on 04/11/2025 10:09 AM - Subject changed from A.08.4. Rubble removal to A.07.4. Rubble removal
-
updated by
Jules Verrier on 04/11/2025 10:09 AM - Subject changed from A.08.3. Demolition of the tiled section on the floor to A.07.3. Demolition of the tiled section on the floor
-
updated by
Jules Verrier on 04/11/2025 10:09 AM - Subject changed from A.08.2. Demolition of the stairs to A.07.2. Demolition of the stairs
-
updated by
Jules Verrier on 04/11/2025 10:09 AM - Subject changed from A.08.1. Demolition of the walls to A.07.1. Demolition of the walls
-
updated by
Jules Verrier on 04/11/2025 10:08 AM - Subject changed from A.08. Dismantle to A.07. Dismantle
-
updated by
Jules Verrier on 04/11/2025 10:08 AM - Subject changed from A.07.1. Paint internal walls to A.06.1. Paint internal walls
-
updated by
Jules Verrier on 04/11/2025 10:08 AM - Subject changed from A.07. Paint walls to A.06. Paint walls
-
updated by
Jules Verrier on 04/11/2025 10:08 AM - Subject changed from A.06.2 . Plaster external walls to A.05.2 . Plaster external walls
-
updated by
Jules Verrier on 04/11/2025 10:08 AM - Subject changed from A.06.1. Plaster interior walls to A.05.1. Plaster interior walls
-
updated by
Jules Verrier on 04/11/2025 10:08 AM - Subject changed from A.06. Wall finish to A.05. Wall finish
-
updated by
Jules Verrier on 04/11/2025 10:07 AM - Subject changed from A.04.3. Flooring tiles finish to A.03.3. Flooring tiles finish
-
updated by
Jules Verrier on 04/11/2025 10:07 AM - Subject changed from A.04.2. Flooring tiles to A.03.2. Flooring tiles
-
updated by
Jules Verrier on 04/11/2025 10:07 AM - Subject changed from A.04.1. Cement screed to A.03.1. Cement screed
-
updated by
Jules Verrier on 04/11/2025 10:07 AM - Subject changed from A.04. Floorings to A.03. Floorings
04/07/2025
-
updated by
Valentina Dell'Infante on 04/07/2025 09:58 AM - Status changed from New to Closed
- % Complete changed from 0% to 100%
-
updated by
Valentina Dell'Infante on 04/07/2025 09:58 AM - Status changed from New to Closed
- % Complete changed from 0% to 100%
-
updated by
Valentina Dell'Infante on 04/07/2025 09:58 AM - Status changed from New to Closed
- % Complete changed from 0% to 100%
-
updated by
Valentina Dell'Infante on 04/07/2025 09:58 AM - Status changed from New to Closed
- % Complete changed from 0% to 100%
-
updated by
Valentina Dell'Infante on 04/07/2025 09:58 AM - Status changed from New to Closed
- % Complete changed from 0% to 100%
04/04/2025
-
updated by
Shrinija Poudel on 04/04/2025 02:33 PM - Subject changed from A.00.2. Milestones to A.00.2. Commencemnet of works
-
updated by
Shrinija Poudel on 04/04/2025 02:03 PM - Parent deleted (
A.04. Wall finish)
- Parent deleted (
-
updated by
Valentina Dell'Infante on 04/04/2025 01:57 PM - Finish date set to 03/07/2025
- Start date set to 02/17/2025
- Duration set to 15 days
-
updated by
Valentina Dell'Infante on 04/04/2025 01:09 PM - Finish date set to 02/21/2025
- Duration set to 1 day
-
updated by
Valentina Dell'Infante on 04/04/2025 01:06 PM - Status changed from New to Closed
- % Complete changed from 0% to 100%
-
updated by
Valentina Dell'Infante on 04/04/2025 01:06 PM - Status changed from New to Closed
- % Complete changed from 0% to 100%
-
updated by
Valentina Dell'Infante on 04/04/2025 01:06 PM - Status changed from New to Closed
- % Complete changed from 0% to 100%
-
updated by
Valentina Dell'Infante on 04/04/2025 01:06 PM - Status changed from New to Closed
- % Complete changed from 0% to 100%
-
updated by
Valentina Dell'Infante on 04/04/2025 01:05 PM - Status changed from New to Closed
- % Complete changed from 0% to 100%
-
updated by
Valentina Dell'Infante on 04/04/2025 01:05 PM - Status changed from New to Closed
- % Complete changed from 0% to 100%
-
updated by
Valentina Dell'Infante on 04/04/2025 12:57 PM - Status changed from New to Closed
- % Complete changed from 0% to 100%
-
updated by
Valentina Dell'Infante on 04/04/2025 12:57 PM - Status changed from New to Closed
- % Complete changed from 0% to 100%
-
updated by
Valentina Dell'Infante on 04/04/2025 12:56 PM - Status changed from New to Closed
- % Complete changed from 0% to 100%
-
updated by
Valentina Dell'Infante on 04/04/2025 12:56 PM - Status changed from New to Closed
- % Complete changed from 0% to 100%
-
updated by
Valentina Dell'Infante on 04/04/2025 12:56 PM - Status changed from New to Closed
- % Complete changed from 0% to 100%
-
updated by
Valentina Dell'Infante on 04/04/2025 12:56 PM - Status changed from New to Closed
- % Complete changed from 0% to 100%
-
updated by
Valentina Dell'Infante on 04/04/2025 12:56 PM - Status changed from New to Closed
- % Complete changed from 0% to 100%
-
updated by
Valentina Dell'Infante on 04/04/2025 12:56 PM - Status changed from New to Closed
- % Complete changed from 0% to 100%
-
updated by
Valentina Dell'Infante on 04/04/2025 12:56 PM - Status changed from New to Closed
- % Complete changed from 0% to 100%
-
updated by
Valentina Dell'Infante on 04/04/2025 12:56 PM - Status changed from New to Closed
- % Complete changed from 0% to 100%
-
updated by
Valentina Dell'Infante on 04/04/2025 12:55 PM - Status changed from New to Closed
- % Complete changed from 0% to 100%
-
updated by
Valentina Dell'Infante on 04/04/2025 12:52 PM - Finish date set to 01/13/2025
- Status changed from New to Closed
- % Complete changed from 0% to 100%
- Start date set to 01/13/2025
- Scheduling mode set to Manual
- Duration set to 1 day
- Working days set to include non-working days
-
updated by
Valentina Dell'Infante on 04/04/2025 12:52 PM - Status changed from New to Closed
- % Complete changed from 0% to 100%
-
updated by
Valentina Dell'Infante on 04/04/2025 12:52 PM - Finish date changed from 03/14/2025 to 01/13/2025
- Status changed from In progress to Closed
- % Complete changed from 15% to 100%
- Duration changed from 45 days to 1 day
-
updated by
Valentina Dell'Infante on 04/04/2025 12:21 PM - Subject changed from A.06. Plaster finish to A.06. Wall finish
-
updated by
Shrinija Poudel on 04/04/2025 12:21 PM - Subject changed from A.08. Dismantle# to A.08. Dismantle
-
created by
Valentina Dell'Infante on 04/04/2025 12:21 PM -
updated by
Shrinija Poudel on 04/04/2025 10:32 AM - Subject changed from A.08. Total Demolition to A.08. Dismantle#
-
updated by
Valentina Dell'Infante on 04/04/2025 09:27 AM - The changes were retracted.
-
updated by
Shrinija Poudel on 04/04/2025 08:52 AM - Dates changed by changes to related Task #110: A.07.3. Demolition of the stairs
- Start date changed from 03/14/2025 to 03/10/2025
- Duration changed from 1 day to 5 days
-
updated by
Shrinija Poudel on 04/04/2025 08:52 AM - Finish date set to 03/10/2025
- Start date set to 03/10/2025
- Duration set to 1 day
-
updated by
Shrinija Poudel on 04/04/2025 08:51 AM - Dates changed by changes to related Task #112: A.07.5. Rubble removal
- Finish date set to 03/14/2025
- Start date set to 03/14/2025
- Duration set to 1 day
-
updated by
Shrinija Poudel on 04/04/2025 08:51 AM - Finish date set to 03/14/2025
- Start date set to 03/14/2025
- Duration set to 1 day
-
updated by
Shrinija Poudel on 04/04/2025 08:49 AM - Finish date set to 03/07/2025
- Start date set to 03/07/2025
- Duration set to 1 day
-
updated by
Shrinija Poudel on 04/04/2025 08:45 AM - Scheduling mode set to Manual
-
updated by
Shrinija Poudel on 04/04/2025 08:44 AM - Dates changed by changes to related Task #96: A.03.3. Flooring tiles finish
- Finish date changed from 02/14/2025 to 02/21/2025
- Duration changed from 5 days to 10 days
-
updated by
Shrinija Poudel on 04/04/2025 08:44 AM - Start date set to 02/21/2025
-
updated by
Shrinija Poudel on 04/04/2025 08:43 AM - Dates changed by changes to related Task #95: A.03.2. Flooring tiles
- Finish date changed from 02/10/2025 to 02/14/2025
- Duration changed from 1 day to 5 days
-
updated by
Shrinija Poudel on 04/04/2025 08:43 AM - Finish date set to 02/14/2025
- Start date set to 02/14/2025
- Duration set to 1 day
-
updated by
Shrinija Poudel on 04/04/2025 08:43 AM - Dates changed by changes to related Task #94: A.03.1. Cement screed
- Finish date set to 02/10/2025
- Start date set to 02/10/2025
- Duration set to 1 day
-
updated by
Shrinija Poudel on 04/04/2025 08:43 AM - Finish date set to 02/10/2025
- Start date set to 02/10/2025
- Duration set to 1 day
-
updated by
Shrinija Poudel on 04/04/2025 08:42 AM - Finish date set to 02/28/2025
- Start date set to 02/17/2025
- Duration set to 10 days
-
updated by
Shrinija Poudel on 04/04/2025 08:41 AM - Scheduling mode set to Manual
-
updated by
Shrinija Poudel on 04/04/2025 08:35 AM - Dates changed by changes to related Task #87: A.02.2. Staircase step/grades
- Finish date changed from 01/20/2025 to 01/27/2025
- Duration changed from 1 day to 6 days
-
updated by
Shrinija Poudel on 04/04/2025 08:35 AM - Finish date set to 01/27/2025
- Start date set to 01/24/2025
- Duration set to 2 days
-
updated by
Shrinija Poudel on 04/04/2025 08:35 AM - Dates changed by changes to related Task #86: A.02.1. Staircase walls
- Finish date set to 01/20/2025
- Start date set to 01/20/2025
- Duration set to 1 day
-
updated by
Shrinija Poudel on 04/04/2025 08:35 AM - Finish date set to 01/20/2025
- Start date set to 01/20/2025
- Duration set to 1 day
-
updated by
Shrinija Poudel on 04/04/2025 08:33 AM - Dates changed by changes to related Task #84: A.01.2. Brick walls Type 2
- Finish date changed from 01/17/2025 to 02/07/2025
- Duration changed from 1 day to 16 days
-
updated by
Shrinija Poudel on 04/04/2025 08:33 AM - Finish date set to 02/07/2025
- Start date set to 01/27/2025
- Duration set to 10 days
-
updated by
Shrinija Poudel on 04/04/2025 08:33 AM - Dates changed by changes to related Task #83: A.01.1. Brick walls Type 1
- Finish date set to 01/17/2025
- Start date set to 01/17/2025
- Duration set to 1 day
-
updated by
Shrinija Poudel on 04/04/2025 08:33 AM - Finish date set to 01/17/2025
- Start date set to 01/17/2025
- Duration set to 1 day
-
updated by
Shrinija Poudel on 04/04/2025 08:32 AM - Finish date set to 01/13/2025
- Start date set to 01/13/2025
-
updated by
Shrinija Poudel on 04/04/2025 08:32 AM - Finish date set to 01/13/2025
- Start date set to 01/13/2025
- Duration set to 1 day
-
updated by
Shrinija Poudel on 04/04/2025 08:26 AM - Finish date changed from 03/07/2025 to 03/14/2025
- Start date changed from 02/28/2025 to 01/13/2025
- Duration changed from 6 days to 45 days
-
updated by
Shrinija Poudel on 04/04/2025 08:23 AM - The changes were retracted.
04/03/2025
-
updated by
Valentina Dell'Infante on 04/03/2025 01:29 PM - Finish date set to 03/07/2025
- Duration set to 6 days
-
updated by
Valentina Dell'Infante on 04/03/2025 08:52 AM - Priority changed from Low to Normal
- % Complete set to 0%
-
updated by
Valentina Dell'Infante on 04/03/2025 08:52 AM - Priority changed from Low to Normal
- % Complete set to 0%
-
updated by
Valentina Dell'Infante on 04/03/2025 08:52 AM - Priority changed from Low to Normal
- % Complete set to 0%
-
updated by
Valentina Dell'Infante on 04/03/2025 08:52 AM - Priority changed from Low to Normal
- % Complete set to 0%
-
updated by
Valentina Dell'Infante on 04/03/2025 08:52 AM - Priority changed from Low to Normal
- % Complete set to 0%
04/02/2025
-
created by
Valentina Dell'Infante on 04/02/2025 11:57 AM -
created by
Valentina Dell'Infante on 04/02/2025 11:57 AM -
created by
Valentina Dell'Infante on 04/02/2025 11:56 AM -
created by
Valentina Dell'Infante on 04/02/2025 11:56 AM -
created by
Valentina Dell'Infante on 04/02/2025 11:55 AM
04/01/2025
-
updated by
Valentina Dell'Infante on 04/01/2025 09:36 AM - % Complete set to 0%
-
updated by
Valentina Dell'Infante on 04/01/2025 09:36 AM - % Complete set to 0%
-
updated by
Valentina Dell'Infante on 04/01/2025 09:36 AM - % Complete set to 0%
-
updated by
Valentina Dell'Infante on 04/01/2025 09:36 AM - % Complete set to 0%
-
updated by
Valentina Dell'Infante on 04/01/2025 09:36 AM - % Complete set to 0%
-
updated by
Valentina Dell'Infante on 04/01/2025 09:36 AM - % Complete set to 0%
-
updated by
Valentina Dell'Infante on 04/01/2025 09:36 AM - % Complete set to 0%
-
updated by
Valentina Dell'Infante on 04/01/2025 09:36 AM - % Complete set to 0%
-
updated by
Valentina Dell'Infante on 04/01/2025 09:36 AM - % Complete set to 0%
-
updated by
Valentina Dell'Infante on 04/01/2025 09:36 AM - % Complete set to 0%
-
updated by
Valentina Dell'Infante on 04/01/2025 09:36 AM - % Complete set to 0%
-
updated by
Valentina Dell'Infante on 04/01/2025 09:36 AM - % Complete set to 0%
-
updated by
Valentina Dell'Infante on 04/01/2025 09:36 AM - % Complete set to 0%
-
updated by
Valentina Dell'Infante on 04/01/2025 09:36 AM - % Complete set to 0%
-
updated by
Valentina Dell'Infante on 04/01/2025 09:36 AM - % Complete set to 0%
-
updated by
Valentina Dell'Infante on 04/01/2025 09:35 AM - % Complete set to 0%
-
updated by
Valentina Dell'Infante on 04/01/2025 09:35 AM - % Complete set to 0%
-
updated by
Valentina Dell'Infante on 04/01/2025 09:35 AM - % Complete set to 0%
-
updated by
Valentina Dell'Infante on 04/01/2025 09:29 AM - Status changed from New to In progress
- % Complete set to 15%
- Start date set to 02/28/2025
- Scheduling mode set to Manual
-
updated by
Valentina Dell'Infante on 04/01/2025 09:24 AM - Priority changed from Low to Normal
-
updated by
Valentina Dell'Infante on 04/01/2025 09:23 AM - Priority changed from Low to Normal
-
updated by
Valentina Dell'Infante on 04/01/2025 09:23 AM - Priority changed from Low to Normal
-
updated by
Valentina Dell'Infante on 04/01/2025 09:22 AM - Priority changed from Low to Normal
-
updated by
Valentina Dell'Infante on 04/01/2025 09:22 AM - Priority changed from Normal to High
-
updated by
Valentina Dell'Infante on 04/01/2025 09:22 AM - Priority changed from Low to Normal
-
updated by
Valentina Dell'Infante on 04/01/2025 09:22 AM - Priority changed from Low to Normal
-
updated by
Valentina Dell'Infante on 04/01/2025 09:22 AM - Priority changed from Low to Normal
-
updated by
Valentina Dell'Infante on 04/01/2025 09:22 AM - Type changed from Task to Phase
- Priority changed from Low to Normal
-
updated by
Valentina Dell'Infante on 04/01/2025 09:20 AM - Type changed from Task to Phase
- Priority changed from Low to Normal
-
updated by
Valentina Dell'Infante on 04/01/2025 09:20 AM - Type changed from Task to Phase
- Priority changed from Low to Normal
-
updated by
Valentina Dell'Infante on 04/01/2025 09:20 AM - Subject changed from A.06.1. Paint internal walls to A.07.1. Paint internal walls
- Priority changed from Low to Normal
-
updated by
Valentina Dell'Infante on 04/01/2025 09:20 AM - Type changed from Task to Phase
- Subject changed from A.06. Paint walls to A.07. Paint walls
- Priority changed from Low to Normal
-
updated by
Valentina Dell'Infante on 04/01/2025 09:19 AM - Subject changed from A.04.2 . Plaster external walls to A.06.2 . Plaster external walls
- Priority changed from Low to Normal
-
updated by
Valentina Dell'Infante on 04/01/2025 09:19 AM - Subject changed from A.04.1. Plaster interior walls to A.06.1. Plaster interior walls
- Priority changed from Low to Normal
-
updated by
Valentina Dell'Infante on 04/01/2025 09:19 AM - Type changed from Task to Phase
- Subject changed from A.04. Plaster finish to A.06. Plaster finish
- Priority changed from Low to Normal
-
updated by
Valentina Dell'Infante on 04/01/2025 09:16 AM - Subject changed from A.05.3. Flooring tiles finish to A.04.3. Flooring tiles finish
-
updated by
Valentina Dell'Infante on 04/01/2025 09:16 AM - Subject changed from A.05.2. Flooring tiles to A.04.2. Flooring tiles
-
updated by
Valentina Dell'Infante on 04/01/2025 09:16 AM - Subject changed from A.05.1. Cement screed to A.04.1. Cement screed
-
updated by
Valentina Dell'Infante on 04/01/2025 09:16 AM - Subject changed from A.05. Floorings to A.04. Floorings
-
updated by
Valentina Dell'Infante on 04/01/2025 09:08 AM - Parent set to A.03. Floorings
-
updated by
Valentina Dell'Infante on 04/01/2025 09:08 AM - Subject changed from A.05.1 Cement screed to A.05.1. Cement screed
- Parent set to A.03. Floorings
-
updated by
Valentina Dell'Infante on 04/01/2025 09:08 AM - Parent set to A.04. Wall finish
-
updated by
Valentina Dell'Infante on 04/01/2025 09:08 AM - Parent set to A.04. Wall finish
-
updated by
Valentina Dell'Infante on 04/01/2025 09:07 AM - Parent set to A.02. Staircase
-
updated by
Valentina Dell'Infante on 04/01/2025 09:07 AM - Parent set to A.02. Staircase
-
updated by
Valentina Dell'Infante on 04/01/2025 09:07 AM - Parent set to A.01. Walls
-
updated by
Valentina Dell'Infante on 04/01/2025 09:07 AM - Parent set to A.01. Walls
-
updated by
Valentina Dell'Infante on 04/01/2025 09:05 AM - Subject changed from Paint internal walls to A.06.1. Paint internal walls
- Parent set to A.05. Paint walls
-
updated by
Valentina Dell'Infante on 04/01/2025 09:04 AM - Subject changed from Paint walls to A.06. Paint walls
-
updated by
Valentina Dell'Infante on 04/01/2025 09:04 AM - Subject changed from Flooring tiles finish to A.05.3. Flooring tiles finish
- Parent set to A.03. Floorings
-
updated by
Valentina Dell'Infante on 04/01/2025 08:52 AM - Subject changed from Flooring tiles to A.05.2. Flooring tiles
-
updated by
Valentina Dell'Infante on 04/01/2025 08:52 AM - Subject changed from Cement screed to A.05.1 Cement screed
-
updated by
Valentina Dell'Infante on 04/01/2025 08:51 AM - Subject changed from Floorings to A.05. Floorings
-
updated by
Valentina Dell'Infante on 04/01/2025 08:51 AM - Subject changed from Plaster external walls to A.04.2 . Plaster external walls
-
updated by
Valentina Dell'Infante on 04/01/2025 08:51 AM - Subject changed from Plaster interior walls to A.04.1. Plaster interior walls
-
updated by
Valentina Dell'Infante on 04/01/2025 08:51 AM - Subject changed from Plaster finish to A.04. Plaster finish
-
updated by
Valentina Dell'Infante on 04/01/2025 08:48 AM - Subject changed from Staircase step/grades to A.02.2. Staircase step/grades
-
updated by
Valentina Dell'Infante on 04/01/2025 08:47 AM - Subject changed from Staircase walls to A.02.1. Staircase walls
-
updated by
Valentina Dell'Infante on 04/01/2025 08:47 AM - Subject changed from Staircase to A.02. Staircase
-
updated by
Valentina Dell'Infante on 04/01/2025 08:47 AM - Subject changed from Brick walls Type 2 to A.01.2. Brick walls Type 2
-
updated by
Valentina Dell'Infante on 04/01/2025 08:47 AM - Subject changed from Brick walls Type 1 to A.01.1. Brick walls Type 1
-
updated by
Valentina Dell'Infante on 04/01/2025 08:46 AM - Subject changed from Walls to A.01. Walls
-
updated by
Valentina Dell'Infante on 04/01/2025 08:44 AM - Subject changed from 1.1.Securing the construction site to A.00.1. Securing the construction site with site fences
-
updated by
Valentina Dell'Infante on 04/01/2025 08:44 AM - Subject changed from Site preparation to A.00.3. Site preparation
-
updated by
Valentina Dell'Infante on 04/01/2025 08:44 AM - Subject changed from Milestones to A.00.2. Milestones
-
updated by
Valentina Dell'Infante on 04/01/2025 08:44 AM - Subject changed from 1.Preparation to A.00. Preparation
-
updated by
Valentina Dell'Infante on 04/01/2025 08:39 AM - Subject changed from Securing the construction site to 1.1.Securing the construction site
-
updated by
Valentina Dell'Infante on 04/01/2025 08:36 AM - Subject changed from Preparation to 1.Preparation
-
created by
Valentina Dell'Infante on 04/01/2025 08:30 AM -
created by
Valentina Dell'Infante on 04/01/2025 08:30 AM -
created by
Valentina Dell'Infante on 04/01/2025 08:30 AM -
created by
Valentina Dell'Infante on 04/01/2025 08:30 AM -
created by
Valentina Dell'Infante on 04/01/2025 08:29 AM -
created by
Valentina Dell'Infante on 04/01/2025 08:29 AM -
updated by
Valentina Dell'Infante on 04/01/2025 08:26 AM - Parent set to A.00. Preparation
-
updated by
Valentina Dell'Infante on 04/01/2025 08:26 AM - Parent set to A.00. Preparation
-
updated by
Valentina Dell'Infante on 04/01/2025 08:25 AM - Type changed from Task to Phase
-
updated by
Valentina Dell'Infante on 04/01/2025 08:25 AM - Parent set to A.00. Preparation
- Duration set to 1 day
-
created by
Valentina Dell'Infante on 04/01/2025 08:25 AM -
created by
Valentina Dell'Infante on 04/01/2025 08:24 AM -
created by
Valentina Dell'Infante on 04/01/2025 08:24 AM -
created by
Valentina Dell'Infante on 04/01/2025 08:19 AM -
created by
Valentina Dell'Infante on 04/01/2025 08:19 AM -
created by
Valentina Dell'Infante on 04/01/2025 08:19 AM -
created by
Valentina Dell'Infante on 04/01/2025 08:18 AM -
created by
Valentina Dell'Infante on 04/01/2025 08:18 AM -
created by
Valentina Dell'Infante on 04/01/2025 08:18 AM -
updated by
Valentina Dell'Infante on 04/01/2025 08:17 AM - Subject changed from Site preparation to Site preparation
- Priority changed from Low to Normal
-
updated by
Valentina Dell'Infante on 04/01/2025 08:17 AM - Priority changed from Low to Normal
-
updated by
Valentina Dell'Infante on 04/01/2025 08:17 AM - Priority changed from Low to Normal
-
updated by
Valentina Dell'Infante on 04/01/2025 08:17 AM - Priority changed from Low to Normal
-
created by
Valentina Dell'Infante on 04/01/2025 08:12 AM -
created by
Valentina Dell'Infante on 04/01/2025 08:10 AM -
created by
Valentina Dell'Infante on 04/01/2025 08:09 AM -
updated by
Valentina Dell'Infante on 04/01/2025 08:09 AM - Subject changed from Create architecturaal house plan to Preparation
-
created by
Valentina Dell'Infante on 04/01/2025 08:02 AM