Valentina Dell'Infante
Activity
Reported work packages: 25
04/07/2025
-
Task #112: A.08.4. Rubble removal (Project: ET4D - Empowering Trainers for Digital innovation in construction Ecosystem)updated on 04/07/2025 09:58 AM
- Status changed from New to Closed
- % Complete changed from 0% to 100%
-
Task #111: A.08.3. Demolition of the tiled section on the floor (Project: ET4D - Empowering Trainers for Digital innovation in construction Ecosystem)updated on 04/07/2025 09:58 AM
- Status changed from New to Closed
- % Complete changed from 0% to 100%
-
Task #110: A.08.2. Demolition of the stairs (Project: ET4D - Empowering Trainers for Digital innovation in construction Ecosystem)updated on 04/07/2025 09:58 AM
- Status changed from New to Closed
- % Complete changed from 0% to 100%
-
Task #109: A.08.1. Demolition of the walls (Project: ET4D - Empowering Trainers for Digital innovation in construction Ecosystem)updated on 04/07/2025 09:58 AM
- Status changed from New to Closed
- % Complete changed from 0% to 100%
-
Phase #108: A.08. Dismantle (Project: ET4D - Empowering Trainers for Digital innovation in construction Ecosystem)updated on 04/07/2025 09:58 AM
- Status changed from New to Closed
- % Complete changed from 0% to 100%
-
updated on 04/07/2025 07:49 AM
- Project status changed from At risk to Finished
04/04/2025
-
Phase #90: A.06. Wall finish (Project: ET4D - Empowering Trainers for Digital innovation in construction Ecosystem)updated on 04/04/2025 01:57 PM
- Finish date set to 03/07/2025
- Start date set to 02/17/2025
- Duration set to 15 days
-
Task #96: A.04.3. Flooring tiles finish (Project: ET4D - Empowering Trainers for Digital innovation in construction Ecosystem)updated on 04/04/2025 01:09 PM
- Finish date set to 02/21/2025
- Duration set to 1 day
-
Task #98: A.07.1. Paint internal walls (Project: ET4D - Empowering Trainers for Digital innovation in construction Ecosystem)updated on 04/04/2025 01:06 PM
- Status changed from New to Closed
- % Complete changed from 0% to 100%
-
Phase #97: A.07. Paint walls (Project: ET4D - Empowering Trainers for Digital innovation in construction Ecosystem)updated on 04/04/2025 01:06 PM
- Status changed from New to Closed
- % Complete changed from 0% to 100%
-
Task #114: A.06.3. Wall tiles (Project: ET4D - Empowering Trainers for Digital innovation in construction Ecosystem)updated on 04/04/2025 01:06 PM
- Status changed from New to Closed
- % Complete changed from 0% to 100%
-
updated on 04/04/2025 12:46 PM
- Project status set to At risk
-
updated on 04/04/2025 08:25 AM
- Name changed from prova to ET4
03/19/2025
-
created on 03/19/2025 02:41 PM